About KRW 359 million awarded for building defects
In our client's defect damages suit against the contractor, about KRW 359 million was awarded through the first instance and appeal, and the contractor's appeal was dismissed.
How the case unfolded
Background
Our client, the building owner, signed a construction contract worth about KRW 6 billion with the contractor. After completion, leaks and other defects appeared, and our client claimed about KRW 1.18 billion in total, combining damages in lieu of repairs and liquidated damages for delay.
Issues and ruling
Relying on expert reports, the court recognized defects such as missing drainage facilities and faulty waterproofing, and rejected the contractor's arguments that it built as the owner instructed and that the claim should be set off. It limited liability to 75 percent considering factors on the owner's side, such as unclear drawings, and rejected the delay claim because the completion deadline had been extended by an amended contract.
Outcome
The first instance awarded about KRW 349 million, and the appeal court added about KRW 9.85 million, for a total of about KRW 359 million plus delay interest. The contractor's appeal was dismissed, and total litigation costs are split 60 percent to our client and 40 percent to the contractor.
This is the outcome of an individual case and does not guarantee the same result in similar matters. Some facts have been generalized to protect the parties involved.
Related practice and case
See the practice area and another success story from the same field.
Tell us what is happening first
Leave an inquiry and we will explain how to proceed after reviewing it. If it is urgent, please call 1577-0448.