KRW 750M construction claim: only KRW 2.26M awarded
Our clients were sued for some KRW 750 million in allegedly unpaid construction fees across several sites. The court awarded about KRW 2.26 million.
The 'joint venture' theory and extra-work claims were almost entirely defeated
Background
Our two clients had hired one contractor for several building projects. The contractor claimed underpayment and extra work, seeking about KRW 375.04 million from each client on the theory that they were partners, and alternatively about KRW 750.08 million in total, split between the two.
The issue
Whether our clients were partners in a joint venture, whether payments had been applied in sequence regardless of site, and whether demolition and extra work were separate contracts.
Our approach
Our clients argued that completed work had been paid in full, including agreed extra costs, and that work the contractor failed to finish had been completed by our clients directly with the building owners, so nothing was owed.
The court's reasoning
The court held that one client's passing reference to the other as a 'partner' did not show an agreement to run a joint business, and rejected the partnership theory. Because our clients had noted site names on transfers and there were site-by-site payment confirmations and full-payment receipts, it found the fees had been settled site by site. There was also no evidence that demolition or extra work were separate contracts. Only at one site, after excluding extra costs a building owner had paid directly, did about KRW 2.26 million remain unpaid.
Outcome
The court ordered one client to pay about KRW 2.26 million plus late-payment interest and dismissed everything else. The contractor was ordered to bear all litigation costs.
What this case means
When working with one contractor across several sites, site-specific payment records and settlement confirmations become key evidence in a dispute.
This is the outcome of an individual case and does not guarantee the same result in similar matters. Some facts have been generalized to protect the parties involved.
Related practice and case
See the practice area and another success story from the same field.
Tell us what is happening first
Leave an inquiry and we will explain how to proceed after reviewing it. If it is urgent, please call 1577-0448.